Peak District
MHH were involved in the formation of a state of the art soccer pitch and multiple viewing areas, this included the movement, in excess, of 50,000 tonnes of Class 2 materials to re-profile the contours and to permit the creation of the plateau. In addition to this we also supplied and created topsoil to the final profiles.
Works also the involved modelling of temporary site access from existing highways, management of existing highways infrastructure, and management and provision of road cleansing vehicles. The site adjoins a busy high school and site restrictions were in place, whilst the health and safety of all stakeholders including the general public was paramount.